Start-up (15/03/2006 - Esbjerg, Danemark)
On 15 March, the CO2-capture industrial pilot unit of the Castor project, coordinated by IFP and financed by the European Commission (FP6), was inaugurated at the Esbjerg power plant (Denmark), operated by Elsam. It is the largest installation in the world that captures CO2 in the flue gases of a coal-fired power station.
The implementation of the Castor pilot is a big step towards demonstrating the feasibility of the new CO2 capture/storage technologies. The process, which enables one tonne of CO2 to be captured per hour, is being tested on a large enough scale to ensure reliable industrial extrapolation.